This weekend we carried out one of the hardest asbestos floor tile removal jobs we have ever undertaken.

We had 35 M2 of asbestos floor tiles to remove in Salisbury, at the Longford Estate offices. This process should have only taken a day for two asbestos operatives, but due to one room in particular, that had a lot of sun beating through the windows, it in fact took 3 days.

We now believe it was harder than the rest due to the sun heating the adhesive below the tiles causing the tiles to become embedded more and more over the years.

We were still able to completely remove all the asbestos floor tiles before the painters were scheduled to be in the room, not holding up the clients works.

This is something we pride ourselves on at Breeze, we will do everything in our power to deliver you service that is responsive and does not affect your building schedule.

We look forward to the next job for Longford Estate in Salisbury, one of our oldest clients.